Major Road Projects in Jammu and Kashmir reviewed

JK News Service by JK News Service
September 30, 2021
in Top Stories
A A
FacebookTwitterWhatsapp

CS directs operationalization of 8 resting places, 3 vehicle holding areas, before 31st October and 3oth November respectively

Asks District Administration/ traffic police to reduce response time for clearing up the traffic congestion on the national highway due to vehicle breakdown/accidents on the national highway to 15 minutes

Fixes timelines for completion of various infrastructural works for dedication to the people of UT

SRINAGAR, SEPTEMBER 30: The Chief Secretary, Dr.Arun Kumar Mehta today chaired a high-level meeting to review the progress of various road projects in Jammu and Kashmir under execution in the different schemes of UT and Central governments.

Administrative Secretaries of Home, Power Development, Public Works (R&B), Mining, besides Divisional Commissioners of Kashmir/Jammu, officers from BRO,NHAI, NHIDCL and concerned Deputy Commissioners participated in the meeting.

It was informed that the Mining department has allottedshort-term permit for extracting the minor minerals to the executing agency to ensure continuous supply of construction material for the Jammu semi-ring road project.

It was further informed that NHAI has constructed crash barriers/parapets at all the critical stretches on Udhampur-Ramban sectionto prevent occurrence of fatal accidents on the National Highway-44.

Dr Mehta directed the installation of such barriers on all critical stretchesof Ramban-Banihal section within a week, especially in the areas prone to frequent landslides and slippages.

To facilitate smooth traffic flow on the Ramban- Banihal stretch of the National Highway, the traffic police and district administration were directed to properly demarcate single-lane driving zones and ensure lane-driving and traffic discipline among the commuters.

The Chief Secretary further directed the District Administration, Ramban to reduce response time to 15 minutes for clearing up traffic snarl ups on the highway caused by vehicles breakdown or accidents by deploying adequate number of cranes on Ramban-Banihal stretch, particularly on the ‘under-construction stretches.

Dr. Mehta further directed NHAI to operationalize 8 rest areas ( wash rooms with mini eating joints) by 31st October, 2021 and all 3 vehicle holding areas/parking bays on NH-44 by 30th November, 2021 to provide ease of travel to the commuters on the National Highway.

He also directed the JKTDC to set up similar facilities on national highway for use by the public by 31st October, 2021.

The Chief Secretary also reviewed the progress on the Z-Morh tunnel; Srinagar-Shopian-Qazigund road; Srinagar semi-ring road project; Chenani-Sudmahadev-Goha road; Jammu-Akhnoor-Poonch road and the upcoming Delhi-Katra expressway and fixed specific timelines for their completion.

Dr Mehta also reviewed the status of works on bridges like Noor Jahan bridge, Brazloo bridge, Gadora bridge among others and gave specific timelines for their operationalisation so that they could be dedicated to the people of the UT.

It was directed that the Srinagar-Shopian-Qazigund along with bypass should be made operational by July, 2022.

The Chief Secretary asked the DC, Udhampur to hand over the 3.3842 hectares land to the executing agency by 7th October, 2021 so that work on the Chenani- Sudhmahadev Goha road is commenced.

District administrations of Jammu and Samba and Kathua were directed to hand over the possession of land for Delhi Amritsar Katra express way to the executing agency by 1st November, 2021.

Dr Mehta further directed that land acquisition for Z morh tunnel should be completed by 15th October 2021.

Similarly, the department was asked to make the Noor Jehan bridge trafficable by 31st December, 2021 besides readying Gadora bridge ready for inauguration by 1st January, 2021.

The Chief Secretary further directed that the condition of the road from Panthachowk to Badami Bagh cantonment should be improved by 15 October, 2021.

The Chief Secretary urged all the concerned Deputy Commissioners to expeditiously resolve all the land acquisition issues bedevilling the construction work on the highway and complete the land acquisition early so that the all ongoing projects are completed within the stipulated timelines.

Previous Post

GoI committed to promoting J&K Tourism worldwide: Union Minister of Tourism Reddy

Next Post

COMBINED ANNUAL TRAINING CAMP CHAMKOTE, TANGDHAR

Next Post

COMBINED ANNUAL TRAINING CAMP CHAMKOTE, TANGDHAR

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

  • Home
  • Our Team
  • About Us
  • Contact Us
Dalgate, Near C.D hospital Srinagar Jammu and Kashmir. Pincode: 190001.
Email us: [email protected]

© JKNS - Designed and Developed by GITS.

No Result
View All Result
  • Home
  • Top Stories
  • Kashmir
  • Jammu
  • National
  • Business
  • Sports
  • Oped
  • World

© JKNS - Designed and Developed by GITS.

This website uses cookies. By continuing to use this website you are giving consent to cookies being used. Visit our Privacy and Cookie Policy.